Gwangyang Port Logistics Complex

Our administration began to construct an international logistics complex (in the hinterland) to promote Gwangyang port to the logistics hub of Northeast Asia from 2003. The construction was completed in July, 2012 with a hinterland of 3.88㎡. Currently, 26 tenants are in operation in the East hinterland while the West hinterland is still attracting businesses.

Classification Port hinterland East West
Construction area 388million㎡(117million pyeong) 195million㎡(59million pyeong) 193million㎡(58million pyeong)
Total project cost 6,719billion 2,843billion 3,876billion
Project period 2003~2012 2003~2008 2006~2012
Constructed by Government, Local government Government, Local government Government, Local government
Bird’s-eye view of the West hinterland in Gwangyang Port

Gwangyang Port Logistics Complex

Ports were built mainly for trade and transportation in the past, but they are now developed to create and use a new urban space. In particular, waterfront has become an essential area with increasing marine leisure activities, and to meet growing requirements for eco-friendly ports. Gwangyang Port created a harmonized space that functions as a part of urban space responding to this new trend. Gwangyang Port is now standing shoulder-to-shoulder with world-class ports.

Location of Waterfront and Buffer Green Zone
Classification area Remark
Waterfront Central Park 35,327 826#
Neighborhood Park No. 1
(Cheolsong Park)
37,935.4 809#
Neighborhood Park No. 2
(Rays-of-Rising-Sun Park)
20,000.0 828#
Neighborhood Park No. 3
(Mulbit Park)
99,400.4 846#
834#
Neighborhood Park No. 4
(not yet decided)
35,327 Area Gwangyang should develop
Neighborhood Park No. 5
(Container Park)
853.9 805#
Total 228,844 -
Buffer Green Zone Buffer Green Zone No.1
Buffer Green Zone No.2
21,093.6 845#
Buffer Green Zone No.3 21,542.00 844#
4,124.6 837#
Buffer Green Zone No.4 5,280.9 835#
Buffer Green Zone No.5 4,774.7 Area Gwangyang should develop
(Estimated area)
Buffer Green Zone No.5 3,149.2 Area Gwangyang should develop
(Estimated area)
Buffer Green Zone No.7 6,467.7 840#
186.6 841#
229.5 842#
Buffer Green Zone No.8 4,007.9 817#
182.6 818#
187.4 819#
Buffer Green Zone No.9 4,163.9 820#
total 71,039.3 -
Overview of Waterfront
Classification Facilities Used by Managed by
Central Park Tennis Court, Parking lot, trail internal users YGPA
Neighborhood Park No. 1 Volleyball and foot volleyball court,
soccer stadium, basketball court
interal employees YGPA
Neighborhood Park No. 2 Visitor center, Winter pond, Palpo garden external users Gwangyang
Neighborhood Park No. 3 Inline skating link, playground external users Gwangyang
Neighborhood Park No. 4 Constructed by Gwangyang external users Gwangyang
Neighborhood Park No. 5 Yeoul madang, Resting place in Forest, Parking lot / internal users YGPA
Neighborhood Park No. 1 Facilities
Classification Standard(m) Scale light available or not Remark
soccer stadium 86x56 1 prohibited, restricted -
Tennis Court - 4 sides open, permitted Clay 2,
Artificial turf 2
basketball court 33x20 1 prohibited, restricted -
Volleyball and foot
volleyball court/
23x14 1 prohibited, restricted -
Neighborhood Park No. 1 Service hours
Classification Summer(March to October) Winte(November to February)
Early morning 05:00~08:00 06:00~09:00
Daytime 08:00~19:00 09:00~18:00
Night 19:00~23:00 18:00~23:00